Godavari Delta System (GDS) is an established old Irrigation System in operation since 1862. The old anicut was constructed by Sir Arthur Cotton during 1857-62 which has served the delta system for more than a century. As it was showing signs of distress, the anicut was replaced by Sir Arthur Cotton Barrage (S.A.C.B.) during the years 1970-88.
Location: | : | Between Dowlaiswaram (V),Rajahmundry Rural(M),East Godavari District and Vijjeswaram (V),Nidadavolu (M), West Godavari District. |
Latitude | : | 81° 45' 00'' East |
Longitude | : | 16° 55' 00'' North |
Ayacut: | : | 10,09,009 Acres ( East and West Godavari District ) |
I.P Contemplated | : | 10,09,009 Acres(Stabilization) |
I.P Created | : | 8,96,533 Acres(Stabilization) |
I.P Utilized (2014-15) | : | 8,96,533 Acres(Stabilization) |
Gross Storage | : | 2.931 TMC |
FRL | : | +13.64 M |
MDDL | : | +9.62 M |
Cropping Pattern | : | Paddy, Sugarcane, Banana, Chillies and Turmeric. ( Khariff and Rabi ) |
Population Benefited | : | 36 Mandals in East Godavari District and 29 Mandals in West Godavari District. |
Present Stage | : | Completed |
Funding Details | : | World Bank Assistance |
Project Starting Date | : | 1970 |
Project Completion Date | : | 1982 |
IRRIGATION POTENTIAL | ||
(A)District wise : | ||
(I) East Godavari District : | ||
a) Godavari Eastern Delta | : | 2,45,333 Acres. |
b) Godavari Central Delta | : | 2,01,898 Acres. |
c) Pithapuram Br Channel | : | 32,507 Acres |
Total | : | 4,79,736 Acres. |
------------------ | ||
(II)West Godavari District | : | 5,29,273 Acres |
Grand Total | : | 10,09,009 Acres. |
Budget for the Year 2015-16 (Modernization of GDS) | : | Plan-30.0000 Crs. Non-Plan-0.2261 Crs. |
Cumulative Expenditure up to 05/2015 | : | 953.4400 Crs. |
------------------ |
Mandal Name | Ayacut in Acres | Mandal Name | Ayacut in Acres |
---|---|---|---|
Anaparty | 9,712 | Alamuru | 12,000 |
Biccavole | 12,157 | Kadiam | 8,913 |
Razole | 15,700 | Kakinada (R) | 9,152 |
Kakinada (U) | 1,105 | Karapa | 18,542 |
Amalapuram | 7,666 | Allavaram | 18,120 |
K.Gangavaram | 18,033 | Kazuluru | 23,961 |
Pedapudi | 22,311 | Rayavaram | 17,237 |
Kapileswarapuram | 17,149 | Samalkota | 23,407 |
Tallarevu | 22,262 | Mandapeta | 15,738 |
Mamidikuduru | 8,480 | Kothapalli | 13,434 |
Pithapuram | 1,937 | Gollaprolu | 5,053 |
Ramachandrapuram | 22,539 | Kothapeta | 13,111 |
I.Polavaram | 18,126 | Thondangi | 3,198 |
Mummidivaram | 9,688 | Inavilli | 11,628 |
Katrenikona | 17,220 | Ravulapalem | 9,787 |
Uppalaguptham | 26,158 | Ambajipeta | 5,636 |
Gannavaram | 7,742 | Malikipuram | 8,417 |
Sakhinetipalli | 12,424 | Atreyapuram | 11,903 |
Total Ayacut | 4,79,736 Acres |
Achanta :14,890 | Attili :8,048 | Ponduru :19,227 | Bhimavaram :38,568 |
Veravasaram :18,933 | Eluru :2,510 | Kalla :32,916 | Eragavaram :19,583 |
Ganapavaram :20,537 | Kovvuru : 83 | Undi :27,670 | Mogalturu :16,194 |
Yelamanchili :14,753 | Nidadavolu :11,637 | Palkolu :17,102 | Palakoderu :18,864 |
Narasapuram :25,978 | Pentapadu :24,910 | Penugonda:13,565 | Penmatra :17,540 |
Bhimadolu :19,504 | Peravali :16,218 | Tanuku :15,232 | Nidamanuru :26,017 |
Tadepalli Gudem :5,116 | Unguturu :20,242 | Akiveedu :22,275 | |
Undrajavaram :18,025 | Denduluru :13,136 | ||
Total Ayacut: 5,29,273 Acres |
The Barrage consists of 4 Arms with 175 Bays with a length of 3.599 Km .
1) Dowlaiswaram Arm with 70 Bays |
2) Ralli Arm with 43 Bays. |
3) Madduru Arm with 23 Bays and |
4) Vijjeswaram Arm with 39 Bays. |
1 | Off take Point | : | Vijjeswaram Head sluice |
2 | No. of Main Canals | : | 11 Nos. |
3 | Total Length of Main canals | : | 357 Km |
4 | Length of distributory net work | : | 2020 Km |
5.(a) | Ayacut (Including Fish Tanks) | : | 5,29,962 Acres |
b) | Fish Tanks | : | 69,962 Acres |
c) | Net Ayacut | : | 4,60,000 Acres |
6 | No. of Mandals Benefited | : | 29 delta Mandals |
7 | No. of Crops | : | 2 Nos. (Khariff and Rabi) |
8 | Water utilization per year | : | Nearly 100 TMC for both the crops |
9 | Drainage basins | : | 3 Nos. |
1)Vasista | |||
2)Upputeru | |||
3)Kolleru | |||
a)Major Drains | : | 21 Nos. Length 409 Km | |
b)Medium Drains | : | 59 Nos. Length 351 Km | |
c)Minor Drains | : | 579 Nos. Length 1513 Km | |
10 | Project Committee | : | 1 No. |
11 | Distributory Committee | : | 20 Nos. |
12 | W.U.A’s | : | 131 Nos. |