ANDRA RESERVOIR PROJECT

Preamble

Constructed across River Champavathi near Andra village, Mentada Mandal, Vizianagaram District and duration of the project is 1983-88 .

Salient Features
River /Source : Champavathi
Location (Village & Mandal) : Aandra(V) Mentada (M)
Estimate / Total Cost : Rs. 3990.00 Lakhs
Year of Starting/Completion : 1983/1998
Reservoir Gross/ Net Capacity in Mcum : 27.75(980 Mcft)/26.4(932 M.Cft)
Ayacut : 3815 Ha (9426 Acres )
Catchment area in Sq.Km : 133.96
Max flood discharge in Cum. : 1189.44
Spillway Details :
Type, Size & Nos : Ogee 10Mx7.5M / 4NO.s
Crest Level : 138.5M
FRL / MWL : 146.0M/146.0M
TBL : 148M
Scour sluice Nos., Size & Sill Level: : N.A
Left Main Canal :
Vent Size & No.s : 2Mx1.5m 1No
Sill Level : 135.2M
Discharge in Cumecs : 2.43
Length Km. : 6.1
Ayacut : 1994 Ha. (4926 Acres)
Right Main Canal :
Vent Size & No.s : 2x1.5 1No.
Sill Level : 135.2
Discharge in Cumecs : 2.43
Length Km. : 2.9
Ayacut : 1821 Ha. (4500 acres
Irrigation Potential : To create an Irriagtion potential of 9426 acres.
Manadals Benefited : Gajapatinagaram, Mentada Manuals.in vizainagaram District.
Components: Earth Dam,Spillway Regulator,Main Canals(LMC, RMC)
Source of Funding: : State Plan
Present Status of Works:: Modernization of Canal system is under Progress.
Land Acquisition:: Nil
Budget & Expenditure (2010-11 UPTO 12/2010)
Budget Estimate: : Rs.40.00 Lakhs.
Expenditure (up to 12/ 2010) : Rs.2.48 Lakhs
Program for 2011-12:: Modernization of Canal system is under Progress.
Index Map