Neeru Chettu Work Wise Progress Details

District : KADAPA
Mandal : OBULAVARIPALLE
Village : BOMMAVARAM
Date of the Report: 06/12/2019
S.No Name Of Work Admin Sanction Desiliting Tank Bund Strengthing Sluices Shutters Poclains Deployed (No's) Bills Paid (Rs in lakhs) Project Status
No. of Works   (Nos) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Cum) Amount   (Rs in lakhs) Qty   (No's) Amount   (Rs in lakhs)
1 Desilting of Pilla vanka to feed Peddaorampadu tank 1 4.5 0 0 0 0 0 0 0 0 0 0 Not Started
2 Desilting of Harijanawada vanka to feed Bommavaram tank 1 4.98 0 0 0 0 0 0 0 0 0 0 Not Started
3 Desilting of Harijanawada Nemalivanka to feed Bommavaram tank 1 4.98 0 0 0 0 0 0 0 0 0 0 Not Started
Total