Neeru Chettu Work Wise Progress Details

District : CHITTOOR
Mandal : GUDIPALA
Village : CHEELAPALLE
Date of the Report: 21/07/2019
S.No Name Of Work Admin Sanction Desiliting Tank Bund Strengthing Sluices Shutters Poclains Deployed (No's) Bills Paid (Rs in lakhs) Project Status
No. of Works   (Nos) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Cum) Amount   (Rs in lakhs) Qty   (No's) Amount   (Rs in lakhs)
1 Desilting of feeder channels to Circar Gariginayani cheruvu of Cheelapalli(V) of Gudipala(M) of chittoor district 1 3.48 0 0 0 0 0 0 0 0 0 0 Not Started
2 Desilting of supply channel from local gunta of basavapalli to checck dam near cheelapalli(V) of guidpala(M) of chittoor dist., 1 5.04 0 0 0 0 0 0 0 0 0 0 Not Started
3 Desilting of feeder channels to circar gariginayani cheruvu of cheelapalli(V) from rasannapalli weir of Gudipal(M) in chittoor district 1 2.646 0.042 1.7 0 0 0 0 0 0 0 0 Completed
Total