Neeru Chettu Work Wise Progress Details

District : CHITTOOR
Mandal : GUDIPALA
Village : GUDIPALA
Date of the Report: 17/07/2019
S.No Name Of Work Admin Sanction Desiliting Tank Bund Strengthing Sluices Shutters Poclains Deployed (No's) Bills Paid (Rs in lakhs) Project Status
No. of Works   (Nos) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Cum) Amount   (Rs in lakhs) Qty   (No's) Amount   (Rs in lakhs)
1 Desilting of supply channel from Molreddy cheruvu to Narayani reddy cheruvu of Gudipala(V) of Gudipala(M) in Chittoor district 1 2.93 0.068 2.75 0 0 0 0 0 0 0 2.25 Completed
2 Desilting of supply channel of Muthuvalluru year gunta of Gudipala(M) in Chittoor district 1 2.09 0.045 1.97 0 0 0 0 0 0 0 1.36 Completed