Neeru Chettu Work Wise Progress Details

District : CHITTOOR
Mandal : IRALA
Village : MUDIGOLAM
Date of the Report: 19/07/2019
S.No Name Of Work Admin Sanction Desiliting Tank Bund Strengthing Sluices Shutters Poclains Deployed (No's) Bills Paid (Rs in lakhs) Project Status
No. of Works   (Nos) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Cum) Amount   (Rs in lakhs) Qty   (No's) Amount   (Rs in lakhs)
1 desilting of supply channel from kakkara gutta to vallasani kunta near maddipatlapalli(V) in irala(M) of chittoor district 1 2 0 0 0 0 0 0 0 0 0 0 Not Started
2 desilting of supply channel from chennarayani cheruvu & M.Paidpalli check dam to jangalapalli kotha cheruvu near jangalapalli(V) in irala(M) of chittoor district 1 3 0 0 0 0 0 0 0 0 0 0 Not Started
3 Desilting of gollavani kunta near kondepalli(v) in irala(m) in chittoor dist., 1 4 0 0 0 0 0 0 0 0 0 0 Not Started
4 Desilting of supply channel from kakkara gutta to vallasani kunta near Maddipatlapalli(V)in Irala(m) of chittoor district 1 2 0 0 0 0 0 0 0 0 0 0 Not Started
5 Desilting of Berivani cheruvu B near maddipatlapalli(V)in Irala(m) of chittoor district 1 4 0 0 0 0 0 0 0 0 0 0 Not Started
6 Desilting of kotha cheruvu near M.Kothur(v) in irala(m) chittoor dist., 1 4.9 0 0 0 0 0 0 0 0 0 0 Not Started
7 DESILTING OF VENGAREDDY CHERUVU B NEAR PANDIGOTTURU (V) IN IRALA (M) OF CHITTOOR (DT) 1 3 0 0 0 0 0 0 0 0 0 0 Not Started
8 Desilting of supply channel from siddeswara vanka to vallam kunta near Gajulapalli(V)in Irala(m) of chittoor district 1 2 0 0 0 0 0 0 0 0 0 0 Not Started
9 Desilting of supply channel from pulluru vani vanka to vallam kunta near gajulapalli(V)in Irala(m) of chittoor district 1 1.5 0 0 0 0 0 0 0 0 0 0 Not Started
10 Desilting of tirukam cheruvu B near chintagumpala palli(v) irala(m) chittoor dist., 1 4 0 0 0 0 0 0 0 0 0 0 Not Started
Total