Neeru Chettu Work Wise Progress Details

District : CHITTOOR
Mandal : K.V.B. PURAM
Village : KANDLURU
Date of the Report: 19/11/2019
S.No Name Of Work Admin Sanction Desiliting Tank Bund Strengthing Sluices Shutters Poclains Deployed (No's) Bills Paid (Rs in lakhs) Project Status
No. of Works   (Nos) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Cum) Amount   (Rs in lakhs) Qty   (No's) Amount   (Rs in lakhs)
1 De-Silting of Kalangi Reservoir and supply channel near Kalangi village 1 8.27 0.194 7.767 0 0 0 0 0 0 0 0 Completed
2 De-Silting of Ponnagunta tank 1 8.26 0.095 7.751 0 0 0 0 0 0 0 0 Completed
3 De-silting of Hanumaiah kandriga tank near Hanumaiah kandriga village 1 4.57 0.05 3.998 0 0 0 0 0 0 0 0 In Progress
Total