Neeru Chettu Work Wise Progress Details

District : CHITTOOR
Mandal : SRIKALAHASTI
Village : YARLAPUDI
Date of the Report: 19/07/2019
S.No Name Of Work Admin Sanction Desiliting Tank Bund Strengthing Sluices Shutters Poclains Deployed (No's) Bills Paid (Rs in lakhs) Project Status
No. of Works   (Nos) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Lakh Cum) Amount   (Rs in lakhs) Qty   (Cum) Amount   (Rs in lakhs) Qty   (No's) Amount   (Rs in lakhs)
1 Repairs to Yarlapudi kalava near Suravaripalli Village in Srikalahasti Mandal. 1 8.2 0 0 0 0 139.21 7.431 0 0 0 0 Completed
2 Reconstruction of Sluice No 2 of Sundi cheruvu of Rajugunta near Rajugunta (V). 1 5.88 0 0 0.002 0.012 94.381 5.139 0 0 0 0 Completed
3 Reconstruction of Sluice No 2 of Repalli tank near Repalli (V). 1 7.2 0 0 0.003 0.015 117.176 6.372 0 0 0 0 Completed
4 Reconsruction of Sluice No.1 of Sundi cheruvu of Rajugunta near Rajugunta Village in Srikalahasti Mandal of Chittoor District. 1 5.91 0 0 0.002 0.013 93.023 5.074 0 0 0 0 Completed
5 Reconstruction (FDR Permanent) of Protection wall to Yarlapudi kalava from Ch 0 to 150 M near Suravaripalli Village in Srikalahasti Mandal of Chittoor District. 1 9.73 0 0 0 0 125.45 6.514 0 0 0 0 In Progress
6 Reconstruction of Sluice No 3 of Rajugunta tank near Rajugunta (V). 1 7.45 0 0 0.003 0.014 123.578 6.546 0 0 0 0 Completed
7 Reconstruction of Surplus Weir No.2 of Rajugunta tank near Rajugunta (V) in Srikalahasti (M) of Chittoor Dist. 1 7.9 0 0 0 0 145.99 6.929 0 0 0 0 Completed
8 FDR to Protection wall to Surplus course of Vellampadu big tank near Suravaripalli (V). 1 8.2 0 0 0 0 148.65 7.508 0 0 0 0 Completed
9 FDR to diversion weir across Repalli kalava near Rajugunta SC Colony (V) in Srikalahasti Mandal of Chittoor District. 1 37.9 0 0 0 0 0 0 0 0 0 0 Not Started
Total